Case Study #3: Discount Retail Chain

Program Highlights

Resource Plus executed 700+ full store remodels and performed 180+ new store setups and expansions.  We designed specific gondola mobilization equipment to fit our client’s remodel needs  We provided specific two man teams to pair with their retailer’s project managers in order to perform fixture replacements, installations, and mobilizations.  Resource Plus personnel managed and coordinated the projects and the client’s remodel personnel with 32 total dedicated personnel and 45,000+ total hours per year.

Results

Because of Resource Plus, the client’s remodel process duration lowered from 11 to 4 days and had 1 to 3 days earlier new store openings/completions.  Our greater efficiencies produce a marked reduction in lost sales due to reduced store down time.